A cafe in England opens late when one approval nobody tracked turns out to have a clock. This walkthrough builds a single register that holds every approval, the body that decides it and the question to put to that body. It then fills the register for an invented unit, one row at a time. Everything applies to England unless stated. It is general information and not legal advice, so put each point to the body named for it.
The author is Blue Feather Designs, a London design studio. Where a point comes from the studio's own practice, the text says so. The studio designs rooms. It does not directly build or fit out, and in its practice the lease is not usually its business.
Step 1: set up the register
Open a spreadsheet or a plain text file. Give it one row for each body, because each body decides only its own items. The columns stay the same on every row. The last three stay blank until you have asked.
body | what it decides | question to ask | clock in the sources | date asked | answer | who replied
Eight rows are enough to start. They are the landlord, the planning authority, building control and the licensing authority. The rest are the food team, the fire assessor, PPL PRS and the council's pavement licensing. Access questions go on the building control row. Add a row whenever your plan brings in another body.
Write the question in full sentences before you send it. A vague request gets a vague reply, and a reply you cannot date is hard to rely on later.
Step 2: meet the example unit
The rest of this walkthrough follows an invented unit. It is an example only and not a real project. Every date and lead time in it is made up, so swap in your own.
The unit is a ground floor shop on a high street, leased by a first time owner. Most trade will be customers who sit in, with some takeaway. The owner wants a fascia sign, two tables on the pavement, music and a licence to sell wine in the evening. The hoped for opening is Monday 12 April 2027.
Step 3: fill the lease and planning rows
The lease sits under every other row, so it goes first. The question for the landlord is which consent each change needs. List the shopfront, the sign, any fixed equipment and the fit out. The example owner takes this row to whoever advises on the lease, since the studio does not usually handle it. The answer goes into the register with its date before any drawings are paid for.
The planning row starts with use classes. The Planning Portal sorts land and buildings in England into classes. A change of use can happen within one class or from one class to another. Depending on the specifics, and on any building work that goes with it, the change may need planning permission or prior approval. The Portal adds that the relevant building regulations must be considered as well.
Two categories matter to a café. Class E(b) is the sale of food and drink for consumption mostly on the premises. That appears to suit a café with mostly sit in customers. A hot food takeaway, where most food is eaten off the premises, is a separate category called sui generis. Public houses, wine bars and drinking establishments sit in that category too.
The example owner plans some takeaway and an evening wine licence, so the question is for the council to settle. The Portal calls its page an introductory guide and not a definitive source of legal information. It also says local rules can change which permissions are needed. The example owner sends this message.
To the local planning authority:
The unit at [address] currently holds [use class, if known].
We plan a café with mostly sit in customers, some takeaway,
and wine served in the evening. Does this plan change the
use class? Does any building work that goes with it need
planning permission or prior approval? Please reply in
writing and tell us how long a decision usually takes.
When the reply arrives, paste the answer, the date and the name of the person who sent it into the row. If the reply gives no timing, write that down as well.
Step 4: fill the sign row
Signs have a consent process of their own. GOV.UK's guidance says displaying an advertisement is subject to a separate consent process within the planning system. The 2007 advertisement regulations for England mainly set it out. The guidance's definition includes a sign, board, awning or blind, whether lit or not. The example owner's fascia sign counts, and so would a projecting sign.
The guidance describes three routes. A few advertisements need no consent if they meet the criteria. Some have deemed consent within further limits. The rest need the express consent of the local planning authority. Displaying an advertisement without consent is a criminal offence. The guidance also notes that other permissions may apply, and gives listed building consent as an example.
Two numbers go into the clock column. Express consent usually lasts 5 years, though the planning authority can grant a longer or shorter period. An applicant can appeal to the Secretary of State if the authority has not decided within 8 weeks. A longer period agreed in writing replaces that. An appeal against a refusal, or against conditions the applicant cannot accept, must normally be made within 8 weeks of the decision.
The question for the sign row is short: which of the three routes does our fascia fall under, and is the building listed? Ask it before anything is ordered, and put the sign on the list from the first drawing.
Step 5: fill the building control row
GOV.UK's building regulations page says you must check whether you need approval before you construct or change a building in certain ways. It stresses that this approval is different from planning permission, and that you might need both. The alterations it lists include a fixed air conditioning system, replacement windows and doors, a heating system and plumbing for a bathroom.
The page speaks mostly to people altering their homes and never mentions cafés. So the register treats it as a pointer and not as a checklist. The page says you could need approval, or special rules, for works it does not list. It tells you to check with a building control body if you cannot decide. That means either the local authority's building control department or a private registered approver. Whoever does the work risks prosecution and a fine if the regulations are ignored.
The example owner puts one question here: which of the planned works need approval, and what drawings does the body want to see? The approval comes from the body. The studio's plans and specifications feed the build, and a designer does not grant approval.
Access also lives on this row. Approved Document M is England's access guidance for buildings other than homes. Its Table 2 gives minimum effective clear widths for doors. For an external door to a building the public uses, it gives 1000mm in a new building and 775mm in an existing one. To measure it, stand square to the wall. Take the gap between the stop on the closing side and the nearest obstruction on the hinge side.
The same document sets out one route to compliance for a bar or serving counter in new work. Part of the working surface is 850mm or lower and permanently reachable by wheelchair users. It says public areas should be accessible, toilets and external terraces included, and staff areas too. Changes of floor level are acceptable if each level stays accessible. The guidance describes new work, so ask building control how it applies to your unit.
For the example unit, the register row for access gets a measurement before the question. Measure the front door, then the counter, then trace the route from the door to the toilet. The numbers go in the question, so the reply can be specific.
Step 6: fill the alcohol and music rows
GOV.UK's alcohol licensing page covers England and Wales. A business that wants to sell or supply alcohol there needs a licence or other authorisation. It comes from a licensing authority, usually the local council. It names late opening cafés among the businesses that might need one. A business that sells alcohol permanently applies for a premises licence. Anyone who plans to sell it, or to authorise its sale, applies for a personal licence. Both go to the council's licensing team with a fee.
The application is shared with what GOV.UK calls responsible authorities. They include the police, the local fire and rescue service, the environmental health authority and the planning authority. The list goes on to the body that protects children from harm, trading standards and Home Office Immigration Enforcement. If the application is properly made and draws no representations, the council must grant it. Conditions must fit the operating schedule and the mandatory conditions. If someone does object, the council decides whether the objection is relevant and may hold a hearing.
The studio's experience is that licences and permissions most often decide the opening date. Alcohol and late opening licences are the usual case. So the example owner asks the licensing team early: do we need a premises licence, and what will each responsible authority look at? The register records who answered and when.
Music is a separate row with a separate body. PPL PRS says that if you play or perform music in a café, you most likely need a music licence. It issues that licence, not the council. Music played only for staff usually needs the licence as well. The page names no exceptions, so the example owner asks PPL PRS directly if the set up is unusual.
Step 7: fill the food team and fire rows
The council's food team holds the register of food businesses. The Food Standards Agency says to register at least 28 days before you start trading, in England, Wales or Northern Ireland. Registering costs nothing, and the council cannot refuse it. The agency recommends against registering much earlier than 28 days before you are ready to start. That gives the row a clock. It is one of the two fixed 28 day clocks in the sources.
The same agency sets out what the premises must be like. Where food is prepared, floors and walls must be smooth, hard wearing and washable, and kept in good condition, cleaned and disinfected. Ceilings should be easy to clean and free from condensation and mould. The whole premises need adequate ventilation, lighting and drainage, and enough washbasins with hot and cold running water. The agency suggests asking your local authority for advice when you choose or change premises.
For a designer, that last point matters before the finishes are chosen. The example owner adds a line to the food team row. It asks the team whether the floor, wall and ceiling finishes in the plan suit a food room.
Fire safety is a duty and not an approval. The Food Standards Agency says you must carry out a fire risk assessment and take fire safety precautions. GOV.UK says the job belongs to the responsible person, who can be an employer, the owner, the landlord or an occupier. The findings must be written down and reviewed regularly. If you lack the time or knowledge, appoint a competent person.
GOV.UK's steps run in order. Identify the hazards and who is at risk. Evaluate and reduce the risks. Record the findings with an emergency plan and training, then review. The fire and rescue authority may give advice. It cannot carry out the assessment for you. The agency adds that fire safety advice is worth taking before you adapt premises. In the register, the fire row names the responsible person and the date the first assessment is due.
Step 8: fill the pavement row
Tables on the pavement need the council's consent. GOV.UK's April 2024 guidance covers pavement licences in England. The council has 28 days from the day after the application, not counting public holidays. That is 14 calendar days for public consultation and 14 to consider and decide. If the council has not decided by then, the licence is treated as granted for two years.
A licence granted that way is not safe from challenge. If it does not meet the legislation or the local conditions, it can be revoked at any time. The guidance names 2000mm as the minimum footway width that should normally be provided. Where that is not feasible, it asks councils to take a proportionate approach. The example owner measures what pedestrians have left with two tables out, and puts that figure in the question.
Step 9: add the clocks and count back
The register now has a clock column with three kinds of entry. Two have a fixed number of days: food registration and the pavement decision, both 28. Signs have the 5 year and 8 week figures. For planning, building control and alcohol, the pages quoted give no timing, so the entry says to ask the body and write the answer down.
Counting back is simple. The example owner opens on Monday 12 April 2027. Twenty eight days earlier is Monday 15 March 2027. That is the latest day for food registration, and the agency advises against registering far ahead of it. The same count gives a starting point for the pavement application. The 28 days exclude public holidays, so the example owner adds a few days to be safe.
Supplier dates go in the same column. The studio plans joinery in advance, since it comes in last. Each item is specified at the start with its lead time, so the studio knows when to order. As an invented example, a quote of 10 weeks for the counter means an order date 70 days before opening. That is Monday 1 February 2027. Ask every supplier for its lead time in writing.
Then read the whole column against the budget and the calendar. In the studio's experience, owners most often go wrong by setting an unrealistic budget or timeline before they speak to a designer. If the dates do not fit, cut scope or move the opening day.
Step 10: read the register for links between rows
The bodies are separate, but the official pages connect several of the rows. Each connection is a reason to ask early.
- Planning and building regulations are different approvals. GOV.UK says you might need both, and the Planning Portal says the relevant building regulations must be considered for a change of use.
- The planning authority is one of the responsible authorities on an alcohol licence application, so a planning question can come up again at licensing.
- The environmental health authority and the local fire and rescue service are on the same list.
- A sign can need listed building consent on top of advertisement consent, according to GOV.UK.
Mark these in the register with a short note in the question column. For the example unit, the planning row reads: asked about use class, signs and wine. The note reminds the owner that the planning authority is also one of the bodies consulted on the alcohol application.
Step 11: handle the usual snags
- A body does not answer. Write the date you asked and ask again. For the pavement licence, silence has a legal meaning, which is a licence granted for two years. For other rows, silence means you do not yet know.
- A body gives no timing. The pages quoted give none for planning, building control or alcohol. Record that, and plan the date as your own estimate.
- Nobody owns the fire risk assessment. It belongs to the responsible person. If that person lacks the time or knowledge, GOV.UK says to appoint a competent person.
- The front door is narrower than the table says. Table 2 is guidance for new and existing buildings, so take the measurement to building control and ask.
- The building turns out to be listed. GOV.UK says listed building consent may be needed in addition to advertisement consent.
Step 12: write down who holds what
Finish with one line for each duty, so no job waits for someone who does not know it is theirs.
- Registration and licences: the business.
- The fire risk assessment: the responsible person.
- Design: the designer.
- Building and fitting out: contractors the client chooses. The studio works with any qualified team, or helps put the job out to tender, and normally recommends at least three quotes.
- The lease: the owner and the landlord.
Planning, building control and licensing decisions come from the bodies named. No designer can promise footfall, sales or reviews. The register does not replace professional advice. It makes a missed date easier to see.
The official pages were read on 23 November 2026. Pages carried over from the earlier coffee shop work were read on 16 November 2026.