Meetings. Meetings everywhere.
What if you could at least ditch the estimation ones? You can. And what you use instead is faster, cheaper, and more reliable.
In many companies you are expected to give a delivery date for a project. And normally that involves a lot of work. A lot! You size up tickets. Check people's availability. Map dependencies. Do the maths. And out comes a delivery date - probably wrong by the time you've finished calculating it.
This is often so time-consuming that teams avoid re-estimation altogether. Which makes the original wrong date even wronger.
Forecasting fixes this. It's faster. Cheaper. And simple enough that you'll re-run it whenever things change.
What is forecasting
In a nutshell, it's a formula. You put in some historical data and a number of tickets. It gives back a delivery date - not just a date, but a date with a confidence level attached.
You are a bit sceptical, right?
I was sceptical at first too. But forecasting is everywhere: stock prices, supermarket inventories, driving routes. The most widely used technique is Monte Carlo simulation.
How it works
It's pure statistics. But there's nothing fancy about it - it's 100% brute force. It runs many, many possible outcomes to find which one is most likely.
Say your team needs to deliver 50 features and you want to know how many weeks it will take. All you need is the number of features the team has shipped in past weeks. What Mr Monte Carlo does is roll the dice, pick a number from that history at random, and keep rolling until he hits 50. Like this:
Number of features done per week (over 7 weeks): 8,7,12,15,14,7,0,10
1st roll: 12 (picked at random)
2nd roll: 7 (at random)
3rd roll: 8 (...)
4th roll: 7
5th roll: 12
6th roll: 10
Total: 12 + 7 + 8 + 7 + 12 + 10 = 56
But that's only one run. Run the same algorithm thousands of times and you get thousands of possible delivery dates. Being 85% confident of a delivery date sounds pretty good, right? Find the 85th percentile - the number below which 85% of your results fall - and that's your date.
You won't do this by hand, of course. Troy Magennis has built a few excellent spreadsheets that do all the work for you, with some sophisticated ways to fine-tune the simulation. Use this one if the project has already started, or this one if it hasn't.
When to use it
Short answer: when Big Boss asks "when will your team deliver the project?"
You can run it at the start of a project or at any point where you need a re-forecast. It helps to have at least the ticket titles written up for what's remaining.
When NOT to use it
Short answer: team planning sessions.
Why? The conversation matters. Going through tickets together as a team - even when the numbers you produce are wrong - creates a shared understanding of the work. It surfaces ambiguities. It helps teams jell. So, do the estimations. But ditch the estimates. Get it?
Going rogue
You'll need to convince your team - and Big Boss - that forecasting is worth trusting. The best way is to not ask for permission first.
Run forecasting quietly, in parallel with whatever your team already does. Let them estimate the usual way. You forecast by yourself. Note both results. After a few months, compare: where did the estimate say you'd be? Where did the forecast say? Where are you actually?
Now tell everyone!
Not every estimation meeting disappears. But the ones where you're just guessing at a date? Those can go.
Filipe Albero Pomar is an engineering manager and speaker based in London. He writes about AI adoption, engineering leadership, and software delivery. Find him at alpomar.dev.